Nick Korhonen
Electrical engineer, power systems. Currently based in Seattle.
Five years experience across transmission planning, real time operations, and industrial construction. Most of it involved interconnection, load growth, and renewable energy solutions. Generally interested in infrastructure, big and small.
The cheapest solution and the best solution are usually not the same one. That gap is the interesting part.
Experience
Engineer, Project Manager
Saginaw Industrial Services · Spring 2025 · Navarre, Florida, with site work in Brewton, Alabama
Seven concurrent electrical capital projects at an operating pulp and paper mill, about $15M total, plus a fast track job replacing seventeen relays. My first long stretch on the construction side rather than the study side.
- Built the field level project schedule from scratch in Microsoft Project and kept it aligned with the program schedule.
- Planned switching and lockout/tagout for a six day segmented outage, including about 36 hours of full de-energization. Mill operations ruled out de-energizing some equipment after the first review, so the plan was rebuilt under time pressure.
- Coordinated five contractor organizations and more than a hundred workers, without formal authority over any of them.
- Field work: grounding grid installation, switchgear verification from 480V through 12kV, SEL relay installation using Rogowski coils, modifications to over a hundred MCC buckets, concrete pour QA, fiber pulling.
- Supported twelve hour executive briefings during the outage and stood in as on-site proxy for an off-site client manager.
- Built at least twenty switching sequences for a six day segmented outage at an operating mill, including about 36 hours of full de-energization, and rebuilt a full day of the plan under time pressure when mill operations ruled out de-energizing some equipment.
- Verification and testing in the field: switchgear from 480V through 12kV, motor rotation testing from the new electrical room, and modifications to over a hundred of the roughly 120 MCC buckets in scope, verifying the work rather than designing it.
- Field work on SEL relay installations using Rogowski coils instead of conventional CTs. A CT means removing equipment to reach the cables and fit it over them, often in confined spaces; a Rogowski coil takes about five minutes, which suits brownfield retrofits.
- Verified the completion of a DCS relocation involving thousands of I/O and terminations, as part of managing the project rather than designing it.
- Handled logistics for a transformer and switchgear set on a helical pile platform, and medium voltage material handling including 600A elbows and surge arrestors.
- Managed documentation uploads in Autodesk Build and checked that the other contractors were sharing what they needed to.
Power Systems Planning Engineer
Great River Energy · 2022 to 2025 · Maple Grove, Minnesota
Generation and transmission cooperative serving 27 member cooperatives within MISO. I was the primary DER contact, which put me between developers, member cooperatives, internal departments, and the RTO.
- Reviewed dozens of DER interconnection requests from 40 kW to 10 MW, and ran local impact studies where the size warranted it. Coordinated agreements, deposits, and results across as many as five parties.
- Wrote the company's first documented DER interconnection procedures. Most requests now resolve at the first screening step.
- Defined the objective, requirements, and study logic for automating the interconnection study process, and directed the data analyst who built it. My estimate is it cut turnaround by around 80 percent.
- Developed the proposal and lifecycle cost case for a 3 MW battery storage microgrid as a non-wires alternative in a rural, environmentally sensitive area. It became part of a successful DOE Grid Resilience and Innovation Partnerships award.
- Ran the non-wires alternative feasibility study for a 345kV expansion. The analysis showed the alternative was not viable and was used in the successful Certificate of Need filing.
- Key contributor to the North American Transmission Forum document Distributed Energy Resources Modeling and Study Practices.
- Presented at an EPRI conference in 2024 on improvements to the EVs2Scale GIS tool and its use in T&D planning studies.
- Built and ran a SharePoint site for an integrated planning effort involving more than twenty engineers from outside companies.
- Reviewed dozens of DER interconnection requests from 40 kW to 10 MW and performed the studies on roughly five to ten of them. Most fell below the study threshold set in guidelines I wrote.
- Ran Great River Energy's side of DER interconnection for requests from 40 kW to 10 MW, aiming to reach MISO's quarterly queue without becoming the critical path. The agreements set the pace more than the studies did: up to five parties signing study agreements and exchanging deposits, sometimes for one to two months.
- Reviewed the results of MISO's regional impact studies on the larger DER projects, and its facility studies where upgrades were needed, and submitted comments and corrections from what I knew of the resource and the system.
- One DER request needed system upgrades: a $60,000 facility study and possibly $3M in upgrades. It was still moving forward when I left.
- Worked from IEEE 1547 constantly in DER interconnection reviews.
- Kept to Great River Energy's limits, as a Transmission Operator, on sharing system information, which keep third-party generators on equal footing, when member cooperatives planning their own DER asked for more transmission data and for advice on where to site it.
- Developed the lifecycle cost case for a 3 MW battery storage microgrid as a non-wires alternative, comparing 36 year depreciating transmission assets against 10 and 20 year lithium-ion replacement cycles. It became part of a successful DOE Grid Resilience and Innovation Partnerships award.
- With a small team, turned upper management's call for grant funded ideas that would help local communities into a defined project: a 3 MW battery storage microgrid as a non-wires alternative. It became part of a successful DOE Grid Resilience and Innovation Partnerships award. My coordination on it was mostly internal.
- Calculated system wide resistance reductions and efficiency gains from capital projects for annual reporting against Minnesota's state conservation mandates.
- Communicated load control impacts and recommended EV charging schedules to smooth system demand, typically lunch hour and overnight at home charging.
- Represented the department on a Future Rate Structures task force.
- Attended the DERTF, MUG and IPWG working groups when DER interconnection and modeling topics came up.
- Reviewed transformer impedances for an area and gave feedback to the team ordering a replacement three years out.
- Presented at an EPRI conference in 2024, on my own and on behalf of another team who weren't there, on improvements to the EVs2Scale GIS tool and its use in T&D planning studies.
Operations Engineer
Otter Tail Power · 2020 to 2022 · Fergus Falls, Minnesota
Operations engineering was me and my manager. Real time support for a control room covering about 5,300 miles of transmission line, most of it 41.6 kV, across western Minnesota and the Dakotas.
- Ran daily N-1 contingency analysis in Siemens ODMS and validated control room switching orders as the last technical check before execution.
- Developed and executed a coordinated transformer tap plan across 41.6 kV and 69 kV to mitigate regional voltage problems. Five transformers adjusted, and the plan is still in place as far as I know.
- Traced widespread low voltage and thermal overloads back to load control restoring demand higher than it otherwise would have been. Worked with the responsible team to change how and when it ran in the affected areas.
- Diagnosed voltage oscillations caused by a wind plant AVR and pursued the fix with the developer.
- Took over the sub-100kV network model and facility ratings database, and found a data entry quirk that had been suppressing a few ratings.
- Led technical troubleshooting on a CIM based ODMS upgrade, clearing data mapping errors that were blocking valid state estimation. Case convergence went from roughly 50 percent to about 90 percent.
- Supported the underfrequency and undervoltage load shedding programs under NERC PRC-006 and PRC-010, and contributed to the annual review of the regional black start plan.
- Reconstructed two operational switching errors in the power flow simulator for root cause review. Both became informal training on the monthly operator calls.
- Reviewed the interconnection of a 100 MW load on the 345kV system, a bitcoin mining operation, for its operating impacts rather than its planning ones. It needed special curtailment programs to maintain system integrity.
- Gave real time support on call outside the normal day, going into the control center after hours when needed.
- Found the cause of sudden large load increases nobody in operations could explain, along with widespread low voltage and thermal overloads: load control was shedding load and restoring it slightly higher than it would otherwise have been. Worked with the responsible team to stop load control in specific areas during specific hours.
- Led technical troubleshooting on a CIM based ODMS upgrade. State estimation had gone months at a time without good results; clearing data mapping errors took case convergence from about 50 percent to about 90 percent by the time I left, with issues remaining but much improved.
- Reconstructed two operational switching errors in the power flow simulator for root cause review, and presented them to leadership. Both became informal training on the monthly calls between operations engineers and operators.
Earlier: power electronics research at UMD in 2019 on an EV DC fast charging topology, and two years processing medical claims data at Xerox from 2015 to 2017. I also ran a small LLC from 2021 to 2025 alongside full time work, doing landscaping and running mining hardware.
Earlier: power electronics research at UMD in 2019 on an EV DC fast charging topology. Designed and captured two layer PCB schematics, sourced the BOM, hand soldered surface mount parts, and programmed microcontrollers for eight synchronized nanosecond scale switching signals, then found the overshoot and timing problems that made the microcontroller unsuitable and moved the team to an FPGA. Before that, two years processing medical claims data at Xerox from 2015 to 2017. I also ran a small LLC from 2021 to 2025 alongside full time work, doing landscaping and running mining hardware.
Toolkit
- Modeling and analysis
- PSS/E for steady state power flow, PSCAD for transients, TARA, DSA Tools, Siemens ODMS, Alstom and GE EMS platforms.
- PSS/E across both utility roles, my deepest tool. Siemens ODMS daily at Otter Tail. PSCAD after a week long vendor course on capacitor bank transients and PIR sizing, used for a few minor studies on existing cases. TARA for DFAX. DSA Tools. Alstom and GE EMS in the control room.
- Project and documentation
- Microsoft Project, Autodesk Build, SharePoint, Nextcloud, Microsoft 365, LibreOffice.
- Standards worked under
- IEEE 1547, NERC PRC-006 and PRC-010, MISO interconnection procedures, FERC and NERC reliability requirements.
- Education
- Bachelor of Science in Electrical Engineering, University of Minnesota Duluth, 2020. Minor in Energy Engineering.
- Certifications
- Engineer in Training, Minnesota. NERC Reliability Coordinator certification, earned 2020 and renewed 2023, now expired.